Rehabilitation of Kechut Dam, construction of new spillway and installation of safety measures

2006-2007
1. The earthwork – 19482 m3.
2. Asphalt carpet – 41233 m2.
3. Concrete and reinforced concrete – 1358 m3.
4. Installation of reinforcement – 71.8 Ton.
5. Shotcrete 2652 m2.
6. Precast reinforced concrete – 38 m3.
7. Insulation of pipelines – 859 m.
8. Cement injection – 8766.5 m2 .
9. External insulation – 3698 m2.