Development of Subsoil Water Drainage System of Yerevan Subway

1995-1998
“Development of Subsoil Water Drainage System at «Zoravar Andranik» Station of the Yerevan Subway”
This project aimed at construction of 1400 m long drainage adit with 8m2 clear section for an export of subsoil water from «Zoravar Andranik» Station to the channel of the Hrazdan River and ceasing the operation of unwatering plants in the vicinity of «Zoravar Andranik» and «Republic Square» Stations.
The underground mining has been carried out under complicated mining and geological conditions in case of abundant influx of subsoil water, when the thickness of ceiling to the residential buildings and communication lines on the surface was minimal (10 – 15 meters).
During the reported period the following basic scopes of works have been implemented:
1. Drifting of underground openings – 433 linear meter.
2. Breaking off of rock – 7439 m3.
3. Placing of concrete and reinforced concrete – 4258.3 m3.
4. Grouting (primary and control) – 36608.3 m2.
5. Pipelines – 2263 m.
6. Reinforcement and steel structures – 69 Ton.
7. Drilling of drainage wells – 4068 m.
8. Lighting during the operation period – 1500 m.
The cost of works amounted to 947247.6 thousand Dram or 2113437 $US.
The Customer: Ministry of Transport of RA, Administration of the Construction of Yerevan Subway.